Monday, November 10, 2008
Saturday, September 20, 2008
Thursday, August 28, 2008
22 August
Sunday, August 3, 2008
Development on July 08
Sunday, June 15, 2008
Update on 15/June
Sunday, May 25, 2008
Improvement Required
We may see the physical skeleton of Vista Gambier is raising in the coming months.
And, we may materialize the verbal promise from LW for the below measures
1. Metal grilled/fencing at corridor area.
2. Visitor Carpark
3. Upgrade package for corner lot with window panel.
And, we may materialize the verbal promise from LW for the below measures
1. Metal grilled/fencing at corridor area.
2. Visitor Carpark
3. Upgrade package for corner lot with window panel.
Update on 25/May

Evening Shine from Bukit Gelugor.

Another View of Ground Floor Slab.

Another view of evening shine.

Clear path has been made for progress.

Standies of column

The footing of the tower crane

Standies of Columns.

Ground floor slab was casted.

Ground Floor slab was casted.

The Tower Crane with LW logo
Told you that the erection of the Tower Crane may be the determining factor for the progress of the construction.
Let's check out the attached pictures for the up-to-date progress for your reference.
Good work, Lereng Wira / Vista Gambier.
Friday, May 2, 2008
Development progress on May