Sunday, May 25, 2008

Improvement Required

We may see the physical skeleton of Vista Gambier is raising in the coming months.
And, we may materialize the verbal promise from LW for the below measures
1. Metal grilled/fencing at corridor area.
2. Visitor Carpark
3. Upgrade package for corner lot with window panel.

Update on 25/May


Evening Shine from Bukit Gelugor.

Another View of Ground Floor Slab.

Another view of evening shine.

Clear path has been made for progress.

Standies of column

The footing of the tower crane

Standies of Columns.

Ground floor slab was casted.

Ground Floor slab was casted.

The Tower Crane with LW logo

Told you that the erection of the Tower Crane may be the determining factor for the progress of the construction.

Let's check out the attached pictures for the up-to-date progress for your reference.

Good work, Lereng Wira / Vista Gambier.

Friday, May 2, 2008

Development progress on May












The pace of the development is getting faster.
The erection of tower crane will be a determining factor of the progress of the slabs and pillar.